If you want to know whether how many days your project is behind schedule showing in the Total Slack field, you should:
1. Double-click the last task or the finish milestone to open the Task Information dialog box.
2. In the Advanced tab:enter the finish date in the Deadline field and select as late as possible in the Constraint type field and then click on the OK button.
3. You will notice a down-arrow sign appears in the Bar Chart area.
4. Save it as baseline.
5. Then use it to track the actual progress.
6. The image above shows the result.