You can use the
Compare Project Versions utility to review differences between the current version and an earlier version of the same project in a detailed report.
1. On the
Compare Project Versions toolbar, click
Compare Project Versions .
If the toolbar is not displayed, on the
View menu, point to
Toolbars, and then click
Compare Project Versions.
2. Under Choose the project versions you want to compare, in the Project version 1 (earlier version) and Project version 2 (later version) boxes, click the versions that you want to compare.
To locate project versions, click
Browse.
3. Under Choose the tables to be used in the comparison, in the Task Table and Resource Table lists, click the tables that contain the data that you want to compare.
If you don't want to compare tasks or resources, click
None.
4. Click
OK.
For purposes of comparison and reporting only, a temporary project is created to display the tasks and resources of the two versions.
5. To keep the report for future reference, click
Save on the
File menu.
Hope you enjoy this new feature in Project 2007.